To provide notification to Project Review Board (PRB) and Technology Change Control Board (TCCB) that UAT has been
successfully completed by the business users.
A completed TCC is submitted to Release Management for review and approval. The certificate will then be
signed by the Release Manager.
The QA Lead is responsible for notifying the PRB of receipt of the completed TCC. Notification is provided to PRB via
the submission of the IT Go-live Checklist.
For TCCB approval, the QA Lead will upload the completed TCC to the appropriate Change Control ticket.