Initiate Pre Go-Live Certification 1 week prior to Go Live date. This includes sending the recertification document and
receiving full access recertification documentation.
Steps
Obtain Go-Live Date
Obtain Go-Live date from Application Owner or Project Manager
Email Recertification Documentation
IAM Specialist emails recertifcation documentation to Application Owner for completion.
Receive Full Access Recertification Documentation
Application owner completes and returns full Access Recertification Documentation to IAM Specialist prior to go-live.
Post Recertification Documentation to SharePoint
IAM Specialist posts completed recertification documentation to SharePoint.