Task: Obtain DR Risk Acknowledgement Sign-off
Recovery Team approval of Risk of not DR Testing.
Relationships
RolesPrimary: Additional: Assisting:
InputsMandatory: Optional:
  • None
External:
  • None
Outputs
Main Description
Recovery Team approval of Risk of not DR Testing. Recovery Team signs off on the risk associated with not testing the application to confirm recoverablity of the recovery strategy.  This task is only completed if the Task: Conduct DR Testing is not completed.
Steps
Fill out the Acknowledgement Form
Distribute the Acknowledgement Form for signatures
Gain approval from Recovery Team and Application Owner
Add application to next DR Test Schedule
Add application to DR Maintenance Schedule
Properties
Predecessor
Multiple Occurrences
Event Driven
Ongoing
Optional
Planned
Repeatable