Task: Conduct DR Testing
DR testing of an application.
Disciplines: Information Security Discipline
Relationships
Main Description

DR testing of an application.

Steps
Conduct DR Pre Go-Live Test
  1. Determine the test date
  2. Gather resources for Pre-Production test
  3. Facilitate Pre-Production test
Document DR Test results
Conduct DR Test results review
Organize a meeting with the Recovery Team and Application Owner to provide results of the DR Test, items for remediation and Lessons Learned.
Coordinate DR Issue Remediation
  1. Create a Service Ticket for the issue requiring remediation.
  2. Re-test recovery strategy once issue is fixed by appropriate resource team.
Obtain DR Test Completion Sign-off from DR Plan Owner
Obtain DR Plan Sign-off from DR Plan Owner
  1. Generate completed DR Plan from LDRPS v10
  2. Route plan for approval by DR Plan Owner
  3. DR Plan Owner provides approval through LDRPS v10
  4. Enter application into regular DR Test Schedule
Add application to DR Maintenance Schedule
Participate in Lessons Learned from DR Testing