 |
| Activities that determine when project is ready to proceed to the Planning Phase. |
|
Purpose
| To determine when a project is sufficiently prepared to proceed to the Planning Phase. |
Relationships
| Roles | Primary Performer:
| Additional Performers:
|
| Outputs |
|
Main Description
| The planning gate helps projects ensure the team is setup for success, schedules are prepared, priorities set and risks
identified. |
Steps
|
Request and Gather Project Documents
Relevant project documents (work products) must be procured from the project team. Documents may include a project
background, risk assessment, project plan, and project schedule among others. An inspector requests project
documents from the Program or Project Manager. The Program or Project Manager, as coordinator and facilitator of
project artifacts, provides the necessary information to the auditor in emails, via SharePoint links, as attachments,
hard copies, etc.
Each work product, (artifact, outcome, or deliverable) provided by the project manager will be retained by
the inspector for purposes of the planning gate.
|
Review the Methodology and Work Products
Determine the process and methodology used by the project team in development of the work products. Since artifacts can
be tailored, the inspector should also identify specific tailoring to determine when deviations from tempaltes,
norms, or accepted changes have occurred. Project teams must provide reasons for deviations and the inspector must
determine if the rationale is warranted and if the deviation is an appropriate solution to meet project needs.
|
Analyze Project State
Using procured work products, tailoring and methodology assessments, analyze the readiness of the project answering
questions such as:
-
Is the project team setup for success?
-
Are the schedul, priorities, and identified risks appropriate?
-
Are actual resource expenditures versus planned expenditures within tolerence?
-
Are the stamdards amd guidelines known and understood by the release team?
|
|
Version and Release
Unified Life Cycle (ULC): 5.1, November 3, 2014
Phase Gates: 1.1, May 27, 2014
Process Engineering Process (PEP): 1.1, May 27, 2014
|
|