| Task: Develop Status Report |
| |
 |
| For this task, a status report is draft with inputs from relevant project areas, then communicated to stakeholders. |
|
Relationships
Main Description
| This activity is performed to create, draft, and communicate the project or program status report. Multiple roles are
involved in the creation of the status report to draw an accurate representation of the health of the project or program at
a particular point in the project life cycle. |
Steps
|
Draft a new project status report
Start with the status report from the previous reporting period, if one exists. If a status report does not exist, use
the template provided to draft a new status report.
|
Gather inputs from project team
Using focused status gathering sessions, collect and record:
-
Activities performed this reporting period
-
Activities planned for the next reporting period
-
Issues that must be addressed
-
Risks that must be mitigated or monitored
|
Communicate the status with the project team
Send the compiled report back to the team and allow at least 4 hours for review and feedback. Once feedack is in, make
appropriate changes to the status.
|
Record the status report in the project document repository
Be sure the final copy is stored in the project's document repository for future reference and for long-term archival.
|
Communicate the status report to stakeholders
Rather than emailing the status report as an attachment, send an email with the link to the report to stakeholders.
|
|