| Task: Develop Effort Estimates |
| |
 |
| When requested, or at specific phases of the lifecycle, the lead or manager will develop effort estimates or refine existing estimates to complete work. |
|
Relationships
| Inputs | Mandatory:
| Optional:
|
| Outputs |
|
Steps
|
Identify Roles
| List all roles for the domain used in the project. |
Resources
Consider the number of resources (testers) available for the project. If the resources are new hires, consider the time for
training and their skill level.
Once completed, submit the estimate to the project management team. |
Identify Key Tasks
| By role and phase of the lifecycle, identify key tasks so that a bulk of the work is accounted. For initial estimates, the
numbers are "rough" and there will be opportunities to refine the estimates in a later phase of the lifecycle. |
Technology/Tools
| If new technology or tools are being implemented, consider the learning curve and training in estimates. Consider the third
party dependencies if any. |
Review Artifacts
| Review appropriate documents, notes, and artifacts that help in determining time and resources required to complete
identified tasks and activities. |
Identify Estimates
| For each role and each task assigned to the role, define the amount of effort (in hours, or days as requested by the
project manager) requried to complete each task. |
Communicate Estimates
| Communicate the total effort for each domain to the project manager for further development of the project plan or project
schedule. |
|
Version and Release
Unified Life Cycle (ULC): 5.1, November 3, 2014
Phase Gates: 1.1, May 27, 2014
Process Engineering Process (PEP): 1.1, May 27, 2014
|
|