| Task: Develop Quality Management (QMM) Effort Estimates |
| |
 |
| When requested, or at specific phases of the lifecycle, the lead or manager will develop effort estimates or refine existing estimates to complete work associated with the QMM domain. |
| Disciplines: Quality Management Discipline |
|
Relationships
| Roles | Primary Performer:
| Additional Performers:
|
| Inputs | Mandatory:
| Optional:
|
| Outputs |
|
Main Description
When requested, or at specific phases of the lifecycle, the QA Lead or QA Manager will develop effort estimates or
refine existing estimates to complete work associated with the QMM domain.
|
Steps
|
Identify Roles
Identify Roles for each task/activity throughout the project schedule
|
Resources
Consider the number of resources (testers) available for the project. If the resources are new hires, consider the time
for training and their skill level.
Once completed, submit the estimate to the project management team.
|
Identify Key Tasks
By role and phase of the lifecycle, identify key tasks so that a bulk of the work is accounted. For initial estimates,
the numbers are "rough" and there will be opportunities to refine the estimates in a later phase of the lifecycle.
|
Technology / Tools
If new technology or tools are being implemented, consider the learning curve and training in estimates. Consider the
third party dependencies, if any.
|
Review Artifacts
Review appropriate documents, notes, and artifacts that help in determining time and resources required to complete
identified tasks and activities.
|
Identify Estimates
For each role and each task assigned to the role, define the amount of effort (in hours, or days as requested by the
project manager) requried to complete each task.
|
Prepare Performance Test Estimates
Prepare Performance Test Effort Estimates using Performance Test Effort Estimation Template.
|
Communicate Estimates
Communicate the total effort for each domain to the project manager for further development of the project plan or
project schedule.
|
|
Version and Release
Unified Life Cycle (ULC): 5.1, November 3, 2014
Phase Gates: 1.1, May 27, 2014
Process Engineering Process (PEP): 1.1, May 27, 2014
|
|