Task: Develop the QA Closure Report
Develop the QA Closure Report for the project Closing.
Purpose
To provide a reference document, which details the status of quality activities as the project enters the final phase to close out the project.
Relationships
RolesPrimary: Additional: Assisting:
InputsMandatory: Optional:
  • None
External:
  • None
Outputs
Main Description
The QA Closure Report will be produced and shared with the project team. The report will be in the form of a dashboard, which is produced in the Test Management Tool (TMT).
Steps
Generate and communicate the dashboard
QA Lead will generate final QA Standard Dashboard.

QA Lead will forward final QA Standard Dashboard to Project Manager.

Project Manager will publish final QA Standard Dashboard on Project SharePoint site, and send a communication to the Project Team Members.
Properties
Predecessor
Multiple Occurrences
Event Driven
Ongoing
Optional
Planned
Repeatable